The Ford Plant was shut down for nine days beginning on Christmas Eve 2018 ending on January 1st, 2019. During the shutdown, we had 32 roofers, seven sheet metal workers and at times two cranes on board to tear-off 246...
Continue Reading →
The scope of work included removing the existing glass, installing a new Kawneer 2000 skylight frame onto the existing framing and installing new glass, and flashing, which consisted of approx. 5,200 sq. ft. of glass (292) sealed units. We began...
Continue Reading →
Gateway at West District – two multi-purpose buildings with main floor retail and seven floors of residential condominiums –  epitomizes the “Total Building Envelope” saying on all of our business cards! This marks our third multi-scope project with developer and...
Continue Reading →
Green roof dirt installation on the third floor (taken just before the sedum). The Alt Hotel, in conjunction with Bockstael Construction, is a multi-scope new construction project in downtown Saskatoon at the River Landing. Being both downtown and by the...
Continue Reading →
Work at the Williston Senior Independent Facility involves installing slope insulation on OSB Sheathing roof deck, 2” Polyiso, Smartboard and torch cap. The biggest challenge on this project from the onset has been the schedule delay from the GC in...
Continue Reading →
Our Hamilton crew pictured below was busy working on three roof sections at the TD Bank totaling 314 squares. The roofs were located 30 storeys from the ground level. Crews removed the BUR roof to expose 2 ply vapor- barrier....
Continue Reading →
Our scope of work included removing the existing roof to expose roof deck, installing new dens deck in duo-tack, peel and stick soprema 130 S VB, two layers of  3” and 2” iso and crickets in duo-tack,  smartboard in duo-tack...
Continue Reading →
The crew of Bruce Neapew, Jason Star, Scott Lavallee (foreman), Camielle Nadeau and Nathan Flett are busy working on the Valleyview Recreation Hub.  This is a new construction, Mod Bit system with all layers glued with a Sopraply base and...
Continue Reading →
Shawn Murray (left) and Will Lyne suited up in the winter clothes and their travel restraint/fall protection. They weren’t going to let the cold stop them from installing flashing’s on Hillcrest Personal Care Home in Brandon, Manitoba....
Continue Reading →
All eyes are on Mark O’Hanley (metals foreman) and his crew on this assignment, likely the most prominent and visible construction site in the downtown core of Victoria, BC. Mark and his crew first visited this landmark site in the...