Amazon is building a huge distribution center called “Project Rose” near the Spokane International Airport. Our scope of work for this project consists of TPO roofing (approx. 7,000 squares on multiple levels), Insulated Metal Wall Panels (approx. 1,300 ea. on multiple elevations), Light Gauge Wind Girts (approx. 28,000 LF of 14 ga. Zee and Cee wind grits) and sheet metal flashings and trim (all roof and IMP associated metals flashings and sealants.)
February was a very rough month for weather which happened to be when we made our biggest push on the IMPs. Other challenges included juggling large crew sizes. We are on an aggressive schedule, expecting to wrap-up mid to late May ’19.