We did 245 squares of 60 mil TPO overlay at Cascades Containerboard Packaging in St. Mary’s, Ontario. The scope of was to remove the Modified Bitumen cap sheet and BUR, while keeping the remains of the existing system in place. We started this project toward the end of 2018, and the weather turned bad quickly causing a two-week delay. The weather took a break, and we got to work we started to remove the existing system to discover it had to be removed to the existing deck and replaced with new vapour barrier and insulation. Replacing the system meant we needed to make sure we had materials onsite and document every area with photos and layouts. Great work and safety on this project, team!
Left to right: Rob Monk, Kyle Smith, Dan Bush, Gord Dennis, Sergio Martinez, Kenneth Williams and Rui Medeiros (foremen).